An interior design timeline should show what must be decided or finished before the next task starts. One duration cannot reliably describe a room refresh, flat renovation and landed rebuilding project. Request a programme based on scope, approvals, site conditions and supply.



The Main Stages
| Stage | Decisions | Output |
|---|---|---|
| Brief and site review | Daily needs, retained items, budget and constraints | Agreed scope and outstanding checks |
| Layout and design | Furniture, services, finishes and alterations | Approved drawings and selections |
| Permissions and procurement | Approvals, lead times and access | Responsibilities and order schedule |
| Site work | Trade sequence and checks | Updated programme and change record |
| Handover | Testing, defects and care | Handover record and follow-up |
Which Tasks Can Overlap?
Some ordering and off-site fabrication can overlap site work after dimensions and specifications are confirmed. An early order is not useful if the layout changes. Ask which decision releases each order or work stage.
Keep Three Dates Separate
- Design approval: drawings and selections agreed.
- Site completion: contracted work ready for checks.
- Move-in or opening: the space suitable for use, including remaining deliveries and operational needs.
These dates need not match. Record their assumptions and update them when scope or supply changes.
Keep a Decision Log
For each unresolved item, record the responsible person, decision date and affected task. Review this with the project lead so a late selection is visible before it disrupts other work.
Check the Property’s Requirements
HDB conditions, condo management requirements and commercial landlord procedures are not interchangeable. Confirm the relevant rules with the appointed team. Our HDB timing guide separates working hours from the wider programme.
Agree Handover and Follow-Up
Schedule a joint inspection, record outstanding items and agree rectification responsibilities. Collect care instructions and applicable warranty documents. Do not treat an early estimate as a guaranteed completion date before the scope and dependencies are established.